How long does dry lining take to install?

Maidstone-specific answer with current 2026 pricing, building regulations, HMO licensing rules and practical advice from our local team.

Get My Free Quote All FAQs

Quick Answer

Programme depends more on the building than the system.

Programme depends more on the building than the system. As a rough Maidstone guide:

  • Single room (walls + ceiling, roughly 15–20 m² of surface): 2–3 days on site, plus 1–2 days for jointing and a further day if you want a plaster skim. The single biggest delay is other trades — if the electrician hasn't finished first-fix, we are waiting
  • Maidstone three-bed Victorian terrace, full re-line including ceilings (typically 80–120 m² of wall, 60–80 m² of ceiling): 5–8 working days for two operatives, plus 2–3 days for jointing and skim. Add a day if the ceilings are direct-fix to old lath that needs sistering
  • Maidstone town centre apartment full re-line (60–80 m²): 4–6 working days. Tower-block lift bookings often cap us to half-day delivery slots, which is the usual source of slippage on these jobs
  • Commercial office fit-out, 200 m² floor plate: 1–2 weeks with a three-person team running partitions and ceilings in parallel
  • Larger commercial (500–1,000 m²): 2–4 weeks depending on the number of meeting rooms, glazed partitions, and acoustic upgrades
  • HMO conversion (4–6 bedsits): 1–2 weeks for the drylining, with fire-rated partitions and acoustic separating walls adding roughly 20% to the programme versus a standard partition layout

What lengthens the programme in practice:

  • Lift access and delivery slot restrictions in Maidstone town centre blocks
  • Out-of-hours working required for occupied commercial space (slower per hour, no weekend uplift)
  • Coordination with other trades — first-fix electrics and plumbing must be done before we board
  • Late specification changes mid-job — every wall revision resets our cut list
  • Drying time on a wet skim (1–2 days before decoration, longer in winter in an unheated Maidstone property)

We provide a written programme with every quote, including the dependencies we expect you to manage (electrician, plumber, decorator) and any inspections we book with Maidstone Building Control.